Contract:

NRC Ballymena - New Build Facility

 

One click access to the Northern Ireland Infrastructure Investment Pipeline.

Download Excel v2007+Format file...

Download PDF Format file...

 

Contract Description:

Contract for the design and build of new facilities at current Ballymena Campus

 

Project:

Northern Regional College (NRC) Capital Developments

Contract Value:

Between £25m and £30m

Stage:

In Procurement

Department:

Department for the Economy

Public Body:

Department Owned (DfE)

   

Procurement

 

Route:

Open Market

Contract Type:

Construction Works

Contract Sub Type:

Construction Works Building

Start:

25/10/2019

End:

Q/E: June 2021

Construction / Delivery

 

Start:

Q/E: June 2021

End:

Q/E: Dec 2024

Contractor:

   

COPE:

CPD

   

Primary Constituency:

North Antrim

Last Updated:

Last Updated: 11 5 2020; All current contracts are updated on a monthly basis.

 

Procurement Advertised:

eTendersNI

   

 

Copyright © 2020 Strategic Investment Board - Development by: Advance Software.